Permit: T08BU00867

Parcel: 141220290


Addresses:

8940 E RITA PARK DR


Inspection Status: Approved

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Permit Number - T08BU00867

Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO

Inspection Status - Approved

Date Description Inspector Results Comments
11/04/2008 FIRE SPKLR - UG, PIPING, HYDRO Approved Fire pumps tested and approved on 10/30/08.
10/31/2008 FIRE SPKLR - UG, PIPING, HYDRO Approved
09/25/2008 FIRE SPKLR - UG, PIPING, HYDRO Not ready for Inspection Just wanted to ask a question about back flows
06/24/2008 FIRE SPKLR - UG, PIPING, HYDRO Cancelled TALKED TO SHAMBAUGH AND SPIRIT UNDERGROUND THEY BOTH CANCELLED
06/23/2008 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 75' of 10" pipe approved by pump house, Fire hydrant by pump house not approved because no hydrant was installed as of this day.
06/16/2008 FIRE SPKLR - UG, PIPING, HYDRO Cancelled INSPECTOR WAS CALLED BY CONTRACTOR AND CANCELLED INSPECTION.
06/11/2008 FIRE SPKLR - UG, PIPING, HYDRO Cancelled INSPECTOR WAS CALLED BY CONTRACTOR AND CANCELLED INSPECTION.
06/05/2008 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Riser #4 stub - APPROVED
UG #7 to Riser #14 - both ends to be uncovered to stub out and tee's on main line - APPROVED
UG #5 to Riser #12 - both ends to be uncovered to stub out and tee's on main line - APPROVED
TEE'S Ok, but unable to see 90 deg elbows to stubs because of concrete poured all around. All ductile iron pipe that was uncovered was wraped with black plastic. STILL NEED TO PRESSURE TEST PIPE AT 225psi FOR 2 HOURS.
Also posted on permits T07CM04797 & T07CM04127 & T08BU00867
06/04/2008 FIRE SPKLR - UG, PIPING, HYDRO Denied UG 10 TO RISER #6 APPROVED
06/03/2008 FIRE SPKLR - UG, PIPING, HYDRO Denied UG 14 to riser #1 - APPROVED
D1 6" line - APPROVED
B #5 10" line - APPROVED
Also posted on permits T07CM04797 & T07CM04127
06/02/2008 FIRE SPKLR - UG, PIPING, HYDRO Denied All of the underground was buried expect approximately 100' on the west end was left open to inspect. Order was given to uncover 10 spots for visual inspection, the following areas are:
UG 14 to riser #1
Riser #4 stub
UG 11 to Riser #5
UG 10 to Riser #6
D1 6" line
B #5 10" line
UG #7 to Riser #14 - both ends to be uncovered to stub out and tee's on main line
UG #5 to Riser #12 - both ends to be uncovered to stub out and tee's on main line
Also posted on permits T07CM04797 & T07CM04127