Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T08BU00801
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/15/2010 | GRADING - INTERMEDIATE | Approved | ||
02/26/2010 | GRADING - INTERMEDIATE | Continued | MET CONTRACTOR (GREG) ON SITE FOR INTERMEDIATE GRADING INSPECTION. PER PHONE CONVERSATION WITH ELIZABETH THE PROPOSED CHANGES TO THE ROCK-RIP RAP HAVE BEEN ACCEPTED (SEE E. NOTES ON 12/15/09) CONTRACTOR NEEDS TO SUBMIT FINAL GEO. REPORT AND SUBMIT TO ELIZABETH PRIOR TO FINAL. REPAIRS TO SIDEWALK IN FRONT OF PROPERTY NEED TO BE COMPLETED PRIOR TO FINAL. COMPLETE STABILIZATION OF DRAINAGE CHANNEL. |
|
12/15/2009 | GRADING - INTERMEDIATE | Approved | Terracon geotechnical letter dated 12-14-09 submitted and is accepted for: soil swale erosion protection areas to have riprap w/ff in lieu of grouted (bedrock areas do not need protection). | |
11/03/2009 | GRADING - INTERMEDIATE | Denied | CONTRACTOR ASKED FOR FIELD APPROVAL TO CHANGE DRAINAGE CHANNEL FROM GROUTED ROCK RIP RAP TO HAND PLACED. REQUEST WAS DENIED FROM ENGINEERING. CONTRACTOR WAS DIRECTED TO HAVE REQUESTED CHANGES APPROVED BY HIS ENGINEER AND SUBMITTED AND APPROVED BY CITY ENGINEER. |