Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2017 | GRADING - INTERMEDIATE | Approved | ||
| 04/23/2008 | GRADING - INTERMEDIATE | Continued | MEETING WITH RICK GREEN THE LANDSCAPE ARCHITECT, CITY PARKS AND SUPERINTENDENT. 1. PROVIDE A 12' INLET AS SHOWN ON THE PLAN AND PROVIDE POSITIVE DRAINAGE (SLOPE) IN CREEK BED. 2. AT FINAL GRADING INSPECTION PROVIDE A LETTER OF CERTIFICATION FROM THE ARIZONA REGISTERED LANDSCAPE ARCHITECT THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE APPROVED GRADING PLAN. 3. REMOVE EXCESS SOIL STOCKPILE. 4. SUGGESTION: PROVIDE ADDITIONAL SOIL AT NORTHWEST CORNER OF SITE TO PREVENT WATER FLOW AROUND CHECK DAM. |
|
| 04/22/2008 | GRADING - INTERMEDIATE | Continued | CREEK BED IS TO NARROW. EXCAVATION NEEDS TO BE AT LEAST 10' WIDE AT INLET AND DEEP ENOUGH TO PLACE THE LARGE RIVER STONES AND ALSO ALLOW FOR DRAINAGE. MEETING WITH PARKS AND LANDSCAPED ARCHITECT TOMORROW AT 9:30 AM. |
|
| 04/21/2008 | GRADING - INTERMEDIATE | Continued | ROUGH GRADING OK FOR CHECK DAMS AND BOOMERANG BERMS AND WALKWAYS. CALL FOR INTERMEDIATE INSPECTION OF CREEKBED. REMOVE ALL SOIL STOCKPILES BEFORE FINAL INSPECTION. |
|
| 04/16/2008 | GRADING - INTERMEDIATE | Continued | CHECKED GRADING PROGRESS | |
| 04/15/2008 | GRADING - INTERMEDIATE | Partial Approval | PRE-CON INSPECTION/SEE ATTACHED COMMENTS I MET WITH BENNY TELLEZ 975-0305 THIS SITE IS LESS THAN AN ACRE AND DOES NOT REQUIRE A SWPPP, HOWEVER, SEDIMENT AND EROSION CONTROL SHOULD BE PROVIDED TO PREVENT STORMWATER POLLUTION. MR. TELLEZ AGREED TO PROVIDE STRAW WATTLE AT THE WEST END OF THE SITE TO PREVENT SEDIMENT TRANSPORT DURING A RAIN EVENT. THE PROJECT IS A WATER HARVESTING/DRAINAGE SWALE AND PARK. |