Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2009 | GRADING - FINAL | Approved | received as-builts and eng. cert. All items complete. | |
| 10/02/2009 | GRADING - FINAL | Denied | Items 1,3,4,6,7 OK, items 2, will be changed on as-built. need to complete 5,9,& 10. | |
| 09/30/2009 | GRADING - FINAL | Denied | Complete the following and call for re-inspection prior to building final. 1) Provide a grouted 5'X5' pad at the trench drain, Sht C-204 2) Install rip rap and expose the end of pipe for the grade inlet sht. C-204 3) Show C.B. on as-built plan and outlet pipe from C.B. Clean all C.B's 4) Provide survey for 1:12 ramp on sht. C-204 to insure compliance. 5) Clean up all construction debris including C>B where grout was dumped. 6) Dress slope west of ramp to football field. 7) Backfill edge of sidewalk at the end of the 1:12 slope. 8) Provide Eng. Cert. for the storm water system 9) Provide as-builts for the grading and site plan. |
|
| 10/06/2008 | GRADING - FINAL | Partial Approval | Met with Al on site, contractor needs to call in for all inspection. Through IVR. | |
| 06/13/2008 | GRADING - FINAL | Partial Approval | Met on site with Magnum Paving. Went over stormwater installation. Contractor needs to maintain 1' on each side of the pipe. | |
| 05/28/2008 | GRADING - FINAL | Partial Approval | Spoke to Alan in regards to pipe installation. I explained I will look at everything outside the building foot print. | |
| 05/27/2008 | GRADING - FINAL | Partial Approval | Spoke to site super in regards to pipe installation. Contractor will need to contact building inspector in regards to pipe under building. |