Permit: T08BU00198

Parcel: 14111002B


Addresses:

8300 E VALENCIA RD


Inspection Status: Continued

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T08BU00198

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Continued

Date Description Inspector Results Comments
04/19/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
02/07/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
10/18/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME. THE RETENTION/DETENTION BASIN DOES NOT WORK FULLY AS SHOWN ON THE APPROVED PLANS, SO MODIFICATIONS MAY HAVE TO BE MADE TO BRING IT WITHIN THE ACCEPTABLE DRAINAGE TIMES PER OUR CURRENT SPECIFICATIONS. THESE MODIFICATIONS WILL HAVE TO BE MADE ON THE REVISED DRAWINGS AND APPROVED PRIOR TO THE CHANGES BEING MADE IN THE FIELD.
08/05/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME. A PRELIMINARY FINAL INSPECTION OF THE SITE WILL BE SCHEDULED NEXT WEEK TO SEE WHAT NEEDS TO BE COMPLETED PRIOR TO THE FINAL INSPECTION BEING CALLED IN.
08/04/2010 STORMWATER FOLLOW-UP INSP Continued THIS SITE WAS CHECKED FOR THE CONDITIONS AFTER OUR PREVIOUS STORMS, THERE ARE SOME MINOR DAMAGES THAT ARE NOTED AND WILL NEED TO BE REPAIRED IN THE NEAR FUTURE, NO REAL CONCERNS AT THIS TIME.
03/18/2010 STORMWATER FOLLOW-UP INSP Continued MET ONSITE WITH CHRIS GENTOR (940-0563) AND DISCUSSED WITH HIM THE NEEDS OF THE SITE. THIS SITE IS CURRENTLY NOT EXPERIENCING ANY ISSUES WITH THE OFF SHED OF WATER AND DEBRIS FROM THIS SITE ONTO OTHER PROPERTY. WE WILL REVISIT THE PLANNED INSTALLATION OF THE STORM WATER CONTROLS NEXT WEEK, WALKING THE SITE TO ENSURE THAT ALL CONCERNS ARE ADDRESSED. ALSO I CONTACTED SOUTHWESTERN CONSULTING ENGINEERING, LLC 628-1062 AND TALKED TO RUSS SHAW ABOUT THE WORK THAT HAS BEEN LACKING ON THIS PROJECT. HE ADVISED ME THAT THE WORK WILL STARTING HEAVIER OVER THE NEXT FEW MONTHS BUT THERE IS NO PROJECTED TIME OF COMPLETION AT THIS TIME. IF HE IS NEEDED IN THE FUTURE HE CAN BE REACHED AT 906-4984 OR AT THE PREVIOUSLY NOTED NUMBER.