Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T08BU00171
Inspection Description - GRADING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2014 | GRADING - FINAL | Approved | ||
| 10/03/2013 | GRADING - FINAL | Continued | DROVE THROUGH THE SITE TO PREPARE MYSELF FOR THE FINAL INSPECTION OF THE SITE NEXT WEEK. MINOR REPAIR WORK IS BEING COMPLETED ON THE EAST SIDE OF THE SITE WHERE THE PARKING LOT CHANGES HAVE BEEN MADE SOUTHEAST OF THE EL SUPRE STORE. DURING THE DRIVE THROUGH OF THE SITE IT WAS NOTED THAT ALOT OF THE TREES HAVE BEEN REMOVED IN THE PHASE 2 PORTION OF THIS SITE IN THE CURACOA PARKING AREA. THESE TREES ARE REQUIRED AND WILL NEED TO BE REPLACED PRIOR TO MY FINAL INSPECTION OF THE SITE. AN INSPECTION OF ALL PARKING AREAS WILL BE PERFORMED TO ENSURE THAT ALL THE TREES ARE IS AS SHOWN ON THE APPROVED PLANS FOR THIS SITE ACCORDING THE ATTACHED LAND USE CODE: 7.6.4. LANDSCAPE STANDARDS B. Vehicular Use Areas The standards in this Section 7.6.4.B apply to all developments that provide more than four motor vehicle parking spaces, except as provided in Section 7.6.4.B.1.c, Exemptions. 1. Canopy Trees in Vehicular Use Areas a. General Standards Within a vehicular use area, one canopy tree is required for each four motor vehicle parking spaces or fraction thereof. (1) The canopy trees must be evenly distributed throughout the vehicular use area. Every parking space must be located within 40 feet of the trunk of a canopy tree (as measured from the center of the tree trunk). |
|
| 11/02/2012 | GRADING - FINAL | Continued | COMPLETE ALL THE WORK AS SHOWN ON THE APPROVED PLANS WHICH WILL INCLUDE BUT NOT LIMITED TO INSTALLING ALL SIDEWALKS AS PREVIOUSLY DISCUSSED, AND THE INSTALLATION OF ALL BICYCLE PARKING LOCATIONS ON THE NORTH AND SOUTH SIDES OF THIS SITE. | |
| 04/19/2010 | GRADING - FINAL | Continued | NO CONCERNS AT THIS TIME. SITE WILL BE CHECKED FOR THE FINAL GRADING ON 4/20-21/2010 AND COMMENTS WILL BE MADE ACCORDINGLY. CONTACTED SCOTT 480-280-9855 AND THEN MET HIM ONSITE TO LOOK OVER THE PLANS THAT HAVE BEEN APPROVED. I WILL PICK UP A COPY OF THE PLANS FROM OUR OFFICE AND WILL UTILIZE THEM IN THE FUTURE INSPECTIONS. | |
| 03/04/2010 | GRADING - FINAL | Not ready for Inspection | LOOKED AT THE SITE TO SEE WHAT SITE WORK HAS BEEN COMPLETED TO ASSIST WITH THE FINAL C OF O RELEASE FOR THE BUILDINGS THAT HAVE BEEN OCCUPIED. CURRENTLY THIS SITE CANNOT BE INSPECTED FOR THE FINAL RELEASES BECAUSE THE CURRENT APPROVED PLANS DO NOT MATCH WHAT HAS BEEN CONSTRUCTED ON THIS SITE. I HAVE PREVIOUSLY ADDRESSED THAT BEFOR A FULL AND FINAL INSPECTION OF THE SITE CAN BE DONE, AN APPROVED SET OF REVISED OR AS-BUILT DRAWINGS WILL HAVE TO BE PROVIDED TO THIS DEPARTMENT FROM THE ENGINEER OF RECORD, THIS HAS NOT BEEN DONE AT THIS TIME. | |
| 05/20/2009 | GRADING - FINAL | Partial Approval | Went by site at 8:00 am and access off of 6th St is open to public, HC parking is in and complete, construction debris is removed from behind the store. | |
| 05/19/2009 | GRADING - FINAL | Correction Required | Site not ready today at 10:00 am paving ongoing in the parking lot, construction activity in the front and back of the building, site not cleaned up with many hazards, entrance off of 6th not open and under construction. I witnessed customers comming out of the store, I told the contractor and owner rep that the store did not have a C of O and that they would have to get the customers out of the store. I called Jim V with a update. Owner asked that I return to the site this afternoon to check on progress. | |
| 05/19/2009 | GRADING - FINAL | Partial Approval | Went back to store at 2:15, Best paving completed work in front of the store and was finishing work in rear of building, 6th street entrance still not open, all construction debris cleaned up from ped. areas, construction fence up. I told contractor and owner rep that the 6th street entrance had to be open prior to opening store to customers, he said it would be open by 5:00pm. Let Jim V and Leeray know what was happening. | |
| 01/26/2009 | GRADING - FINAL | Correction Required | Contractor needs to address southwest corner of building. contractor unable to maintain 2' setback with 19' roadway. Needs to address at 201 N. Stone. |