Permit: T08BU00171

Parcel: 11901051L


Addresses:

295 W 40TH ST


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T08BU00171

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
03/12/2014 STORMWATER FOLLOW-UP INSP Approved
08/24/2011 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
10/25/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
04/19/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME. SITE WILL BE CHECKED FOR THE FINAL GRADING ON 4/20-21/2010 AND COMMENTS WILL BE MADE ACCORDINGLY. CONTACTED SCOTT 480-280-9855 AND THEN MET HIM ONSITE TO LOOK OVER THE PLANS THAT HAVE BEEN APPROVED. I WILL PICK UP A COPY OF THE PLANS FROM OUR OFFICE AND WILL UTILIZE THEM IN THE FUTURE INSPECTIONS.
03/04/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME.
01/26/2009 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address mud hole southeast corner. Tracking out on to 6th. Ave.
10/31/2008 STORMWATER FOLLOW-UP INSP Correction Required Contractor did not address Correction Notice from 10/24/08. Issued new Correction Notice today contractor has 2 days to address items. If not addressed will issue Notice of Violation. Spoke to Scott site super in regards to.
10/24/2008 STORMWATER FOLLOW-UP INSP Correction Required Issued Correction Notice. Contractor has 7 days to address:
1- Install construction entrance. (Per SWPPP)
2- Stake down all wattle per design.
3- Clean all wash out from site.
4- Provide wash out area for sub-contractors and ensure use.
5- Contractor stockpilling more then 50 cubic yards of material, need to obtain stockpiling permit.
6- Sweep all track out into public parking area.
7- Contain all areas disturbed by construction with SWPPP controls.
8- Keep all construction activity and material separated from public access.
If contractor does not address items will issue a Notice of Violation or Stop Work Order. Spoke to Scott site super.
10/23/2008 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address all wash out on site and clean track out.
08/28/2008 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to install all controls per design.