Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T08BU00093

Parcel: 14029212B

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
10/28/2009 GRADING - FINAL Approved Bike rack installed, Cb's cleaned, received eng. cert. as-builts submitted. Approved
10/22/2009 GRADING - FINAL Denied Complete the following items and call for re-inspection.
1) Submit as-built drawing to Eng. counter at 201 N Stone.
2) Provide Eng. Cert for storm system.
3) Provide 5 bike parking stalls per site plan.
4) Clean all C.B's
5) Remove construction trailer and porta-potty.
01/29/2009 GRADING - FINAL Partial Approval Per Jason G. PAAL's ok on east side of building. Traffic flow to be one way.
01/12/2009 GRADING - FINAL Correction Required Contractor needs to address PAAL's less then 24'.
10/27/2008 GRADING - FINAL Partial Approval Per Matt Flick, OK to place sign in right-a-way. Per e-mail sent on 10/27/08.