Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2009 | GRADING - FINAL | Approved | Bike rack installed, Cb's cleaned, received eng. cert. as-builts submitted. Approved | |
| 10/22/2009 | GRADING - FINAL | Denied | Complete the following items and call for re-inspection. 1) Submit as-built drawing to Eng. counter at 201 N Stone. 2) Provide Eng. Cert for storm system. 3) Provide 5 bike parking stalls per site plan. 4) Clean all C.B's 5) Remove construction trailer and porta-potty. |
|
| 01/29/2009 | GRADING - FINAL | Partial Approval | Per Jason G. PAAL's ok on east side of building. Traffic flow to be one way. | |
| 01/12/2009 | GRADING - FINAL | Correction Required | Contractor needs to address PAAL's less then 24'. | |
| 10/27/2008 | GRADING - FINAL | Partial Approval | Per Matt Flick, OK to place sign in right-a-way. Per e-mail sent on 10/27/08. |