Inspection History: GRADING - INTERMEDIATE
Permit Number - T08BU00070
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/03/2009 | GRADING - INTERMEDIATE | Approved | MOST SITE WORK HAS BEEN COMPLETED PER APPROVED PLANS - WORK REMAINING IS LISTED INDER THE FINAL GRADING INSPECTION DATED 10/20/09 | |
09/25/2009 | GRADING - INTERMEDIATE | Continued | 11" CONCRETE APRON INSTALLED, MOST BLDGS HAVE BEEN COMPLETED. SWALES ALONG EAST PERIMETER NEED TO BE INSTALLED, SITE MUST BE HYDROSEEDED OR STABILIZED IN SOME MANER PRIOR TO FINAL APPROVAL. PARKING AREA ALONG SOUTH SIDE IS COMPLETED, MOST HC RAMPS IN, SIDEWALKS INSTALLED. ROOF DRAIN TIE-INS HAVE BEEN COMPLETED. VAULT AT RET/DET BASIN ON WEST SIDE COMPLETED. |
|
04/09/2009 | GRADING - INTERMEDIATE | Continued | TOOK PICS OF INSTALLED STORM WATER OIL/WATER SEPARATOR VAULT. | |
04/02/2009 | GRADING - INTERMEDIATE | Continued | BEGINING INSTALLATION OF STORM WATER SEPARATOR BOX ALONG WEST CHANNEL AND BASIN AREA (SEE PICS) | |
03/23/2009 | GRADING - INTERMEDIATE | Continued | CONTRACTOR DOING PREP WORK FOR STORM SEWER OIL/WATER SEPARATOR INSTALLATION AT EXISTING RET/DET BASIN. SEPARATOR WILL TIE INTO AN EXISTING 3' X 5' BOX CULVERT LOCATED ON THE EAST WALL OF THE EXISTING BASIN. |
|
03/05/2009 | GRADING - INTERMEDIATE | Continued | UTILITY TIE-INS BEING DONE, NO SITE WORK BEING DONE AT THIS TIME | |
02/12/2009 | GRADING - INTERMEDIATE | Continued | CHECKED REBAR LAYOUT AND TOOK PICTURES OF CATCH BASIN AT TRUCK WASH BLDG. SITE WILL HAVE 3 CATCH BASINS/1 EXISTING AND 1 OIL/WATER SEPARATOR |
|
02/10/2009 | GRADING - INTERMEDIATE | Continued | REVIEWED APPROVED GRADING PLAN WITH SUPERINTENDENT. ENSURE YOU CONTACT ENG. INSPECTOR WHEN STORM DRAIN PIPING IS INSTALLED. | |
02/05/2009 | GRADING - INTERMEDIATE | Continued | NEED TO INSPECT 18" STORM DRAIN PIPE INSTALLED AND SHOWN ON THE APPROVED GRADING PLAN. NEED TO INSPECT CONCRETE GRAVITY SOLIDS SEPARATOR BUILT AND INSTALLED AT OUTLET OF STORM DRAIN PIPE. |