Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/26/2007 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 12/19/2007 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* NO TEST ON SYSTEM, READ ALL NOTES & COMPLY A REFEE COULD BE APPLIED TO THIS INSPECTION FOR FAILURE TO COMPLY |
|
| 12/18/2007 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* SHALL RETEST GAS PIPING SYSTEM AND HAVE 10PSI MINIMUM ON TEST GAUGE AT TIME OF REINSPECTION AS REQUEST ON 12/17/07 INSPECTION SHEET. SHALL PROVIDE BONDING OF BUILDING GAS PIPING AS REQUESTED ON 12/17/07 INSPECTION SHEET. FAILURE TO COMPLY CAN RESULT IN REINSPECTION FEES. |
|
| 12/17/2007 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. SHALL SUPPORT GAS PIPING AT METER AND DROP AT WATER HEATER/STOVE 2. VENT FROM WATER HEATER TO HAVE MINIMUM 1" CLEARANCE FROM ROOF (FLAMMABLE MATERIAL) AND TERMINATE MINIMUM 2' ABOVE TOP OF ROOF 3. PROVIDE BLOCKING UNDER GAS PIPING ON ROOF STRUCTURE AND SECURE PIPING TO BLOCKING. 4. PROVIDE BONDING OF BUILDING GAS PIPING 5. SHALL PROVIDE WEATHERPROOF ENCLOSURE FOR WATER HEATER. |