Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2010 | PLUMBING - FINAL | Approved | IVRS - Inspection :* 1) IF YOU ARE NEEDING A GAS CLEARANCE. THEN I WILL NEED TO INSPECT SYSTEM |
|
| 12/18/2007 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE BONDING PER NOTE #5 FROM 12/10/07 INSPECTION |
|
| 12/10/2007 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. TIE IN YARD PIPING TO EXISTING BUILDING PIPING AND TEST ENTIRE GAS SYSTEM 2. PROVIDE AGA OR CSA APPROVED GAS VALVES AT ALL APPLIANCES 3. PROVIDE 3-GALV SCREWS AT EACH JOINT OF FLUE VENT PIPING FROM WATER HEATER/FURNACE 4. WATER HEATER TEMPERATURE & PRESSURE RELIEF DRAIN SHALL BE APPROVED PIPING MATERIAL (CPVC, COPPER, GALVANIZED PIPE) GRAVITY DRAIN TO DAYLIGHT TERMINATING AT 90 DEG. DOWN 6" TO 24" FROM FINISH GRADE ELEVATION 5. PROVIDE BONDING OF BUILDING GAS PIPING |