Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2007 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 10/05/2007 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1. SHALL TEST GAS SYSTEMS IN ENTIRETY 2. SHALL PRIME THEN TAPE NEW PIPING UNDERGROUND TO 6" ABOVE FINISH GRADE. 3. WATER HEATERS TO BE INSTALLED CORRECTLY IN WEATHERPROOF ENCLOSURES 4. SHALL PROVIDE APPROVED WATER PIPING WITH EXPOSURE OF PIPING 5. SHALL PROVIDE AGA OR CSA APPROVED GAS VALVES AT ALL GAS APPLIANCES 6. PROVIDE PERMIT FOR NEW WALL HEATER 7. COMPLETE WORK LIST MAY NOT BE COMPLETE 8. PROVIDE BONDING OF GAS PIPING |