Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/26/2007 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 04/23/2007 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* FROM METER THRU SYSTEM TEST OK 1. VENT FROM WATER HEATER & FURNACE TO BE FULL SIZE DOUBLE WALL THRU ROOF 2' ABOVE AIR INTAKES WITH APPROVED VENT CAP. PROVIDE 3-GALV SCREWS AT EACH JOINT OF VENT PIPING. 2. WATER HEATER TO HAVE FULL SIZE T&P DRAIN GRAVITY DRAIN TO DAYLIGHT OR PROVIDE CITY SIGNED PETITION OF APPEAL ON SITE WITH CORRECT INSTALLATION FOR ALTERNATE FORM OF T&P RELIEF. |
|
| 04/17/2007 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 1" PE YARD LINE OK IF SIZED PROPERLY EXTEND 1" TO ABOVE GRADE PROVIDE ACCESS TO ALL GAS APPLIANCES PROVIDE TEST ON ENTIRE SYSTEM |