Inspection History Details
Permit: T07PL00583
Inspection Status: Approved
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2007 | SITE - SEWER | Approved | ||
| 09/11/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE TESTING STANTEC PAPERWORK IN ORDER |
|
| 09/10/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* STANTEC PAPERWORK IN ORDER MANHOLE VACUUM TESTING |
|
| 09/07/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CANCELLED |
|
| 09/06/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CANCELLED |
|
| 08/30/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. STANTEC PROVIDING TESTING LIST, WORKED WITH STANTEC ON 8" SDR 35 PSI TEST FROM FIRST MANHOLE INSIDE LOT AT NORTH END OF LOT. STANTEC TO PROVIDE RESULTS. 2. HCS FROM MANHOLE #4 TO PAD #4 OK |
|
| 08/27/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. PAD #2 HCS PIPING OK 2. PAD #3 HCS PIPING OK 3. MANHOLE #5 TO #4 PIPING OK 4. ALL PIPING AND MANHOLES TO BE TESTED AT LATER DATE |
|
| 08/22/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* HCS TIE IN, PAD #112 SHOPS #5 & PAD #1 AND SHOP #6, TIE IN AT MINOR #6 OK NEED TO INSPECT PIPING |
|
| 08/21/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
| 08/16/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. MANHOLE #8 TO #7 PIPING OK HCS TO BE INSTALLED AT LATER DATE 2. MANHOLE #7 TO #6 PIPING OK 3. ALL TESTING FOR ALL OF JOB TO BE DONE AT LATER DATE 4. #3 HCS OK |
|
| 08/14/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CANCELLED |
|
| 08/13/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. MANHOLE #9 TO #8 NO HCS PIPING OK UNCOVER #3 TO INSPECTED HCS 2. MANHOLE #20 THRU #14 OK OTHER THAN #3 |
|
| 08/10/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) HCS MANHOLE #12 TO #11 OK, TO BE TESTED AT LATER DATE 2) FROM MANHOLE #12 TO #10 SDR 8" PIPING TRACER WIRE AND BUDDING OR TO BE ? FINAL AT LATER DATE 3) ? HCS SOUTH OF MANHOLE #19 |
|
| 08/09/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* UNCOVER FITTING AND MAIN PIPING FOR INSPECTION |
|
| 08/03/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #14 TO #13 TO #12 TRACER WIRE OK HCS TO BE INSTALLED AT A LATER DATE |
|
| 07/31/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* RAIN OUT |
|
| 07/19/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* PROVIDE CITY APPROVED PLANS ON SITE ALL PRIVATE SEWER TO BE INSPECTED BY THE CITY OF TUCSON IT APPEARS THAT PRIVATE SEWER HAS BEEN COVERED WITHOUT INSPECTION BY CITY OF TUCSON |