Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2007 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 03/09/2007 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* SCOTCH KOTE PIPE REQUIRED BELOW GRADE PRIME THEN WRAP TOOL MARKS AND FITTINGS PIPE SHALL HAVE 12" OF COVER AND BE CONTINUOUSLY SUPPORTED RETEST SYSTEM AT WATER HEATER CORRECTLY INSTALL TEMPERATURE & PRESSURE RELIEF DRAIN. PIPE TO BUILDING EXTERIOR W/APPROVED MATERIALS. GRAVITY DRAIN AND TERMINATE 6" ABOVE GRADE SECURE VENT W/GALV SHEET METAL SCREWS INSTALL SEDIMENT TRAP ON GAS SUPPLY |
|
| 03/06/2007 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1. UNCOVER UNDERGROUND GAS PIPING AND PROVIDE PRIMER AND 10 MIL TAPE 2. TEST GAUGE SHALL HAVE 1/10 PSI INCREMENTATION. |