Inspection Status: Approved
Inspection History: INSP - AST/UST
| Date |
Description |
Inspector |
Results |
Comments |
| 08/06/2007 |
INSP - AST/UST |
|
Approved |
The stationary diesel tank has been removed. The oil tank has the proper venting installed. Permit issued for the oil tank. |
| 07/16/2007 |
INSP - AST/UST |
|
Correction Required |
Attempted to contact david. No reply |
| 06/11/2007 |
INSP - AST/UST |
|
Correction Required |
Pre citation given to David. Compliance is due by June 29, 2007 |
| 06/07/2007 |
INSP - AST/UST |
|
Continued |
Called David, he has not returned my call. The city permit has been applied for and electrical has not been passed yet. 500 gallon DIESEL Tank is in place, bollards and venting is approved. Lpg tank is also in place, no electrical required, bollards approved. The old Diesel tank is still on site, empty and protected from vehicles. re- inspect next week |
| 04/19/2007 |
INSP - AST/UST |
|
Continued |
Site inspection performed. David and Lee were unavailable, The new 500 gallon diesel AST is in place. The old tank is missing. Union distributors installed the new tank. |
| 04/05/2007 |
INSP - AST/UST |
|
Continued |
Met with Lee, explained set back, vehicle impact, and venting requirements for the ast's. |
| 04/04/2007 |
INSP - AST/UST |
|
Continued |
Meeting with David. Class IIIB,and LPG tank are going to be moved. Provided distance requirements. Still waiting on union distributors to provide fuel tank and cut sheet to continue the permit process. Tank is to be delivered in the next 3 days. |
| 03/21/2007 |
INSP - AST/UST |
|
Continued |
Met with David. The permit process has been started. Union distributors is building new tanks. |