Inspection Status: Approved
Inspection History: INSP - AST/UST
| Date |
Description |
Inspector |
Results |
Comments |
| 12/12/2007 |
INSP - AST/UST |
|
Approved |
Final approved. Checked for leaks and tested all emergency stops and resets. All passed. |
| 11/26/2007 |
INSP - AST/UST |
|
Continued |
Approximately 2 weeks from final inspection |
| 10/08/2007 |
INSP - AST/UST |
|
Continued |
Piping inspection complete. Pressure and soap test performed. no leaks detected. |
| 09/06/2007 |
INSP - AST/UST |
|
Continued |
Installed 4 tanks. All tanks arrived under vacuume and were re-checked after the backfill process. |
| 09/04/2007 |
INSP - AST/UST |
|
Continued |
SI- Tank hole being dug. Tanks now to be set 9-6-07 |
| 07/23/2007 |
INSP - AST/UST |
|
Continued |
Inspection report was generated, not ready, this will be a Gas City and they have not started excavation yet. Combustibles on site, hydrants wet. |
| 01/08/2007 |
INSP - AST/UST |
|
Continued |
Inspection report was generated, not ready, this will be a Gas City and they have not started excavation yet. |