Case: T07DV11963

Parcel: 107010010

Inspection Status: Approved

Inspection History: INSP - FOLLOW UP CODE ENFORCE

Date Description Inspector Results Comments
05/07/2009 INSP - FOLLOW UP CODE ENFORCE Approved WATER LINES ARE DONE AND FINAL WAITING. CASE CLOSED
02/11/2009 INSP - FOLLOW UP CODE ENFORCE Approved Work is almost completed. Waiting for final inspction with DSD. Fire hydrant to still be installed. Follow-up in 30 days.
01/09/2009 INSP - FOLLOW UP CODE ENFORCE Approved WORK IS ONGOING, INSPECTION HAS BEEN MADE BY DSD. CHECK BACK IN 30 DAYS
11/11/2008 INSP - FOLLOW UP CODE ENFORCE Approved WORK IS BEING DONE, NEED TO CHECK ON INSPECTIONS. T08CM01659(T08PL00838) WORK IS BEING DONE AND ON PART IS INSPECTED AND COVERED WORK ON NEXT PHASE. CHECK BACK IN 60 DAYS.
10/13/2008 INSP - FOLLOW UP CODE ENFORCE Approved WORK HAS BEEN STARTED. CHECK BACK IN 30 DAYS.
09/12/2008 INSP - FOLLOW UP CODE ENFORCE Approved IS GETTING BIDS TO HAVE WORK DONE. WILL CHECK BACK IN 30 DAYS.
02/20/2008 INSP - FOLLOW UP CODE ENFORCE Approved Recivied an E-mail from Ms. Hopson, and she hope to have the plans to DSD early next week, the contract who did the wrok is dragging his feet in getting the plans. Will check with her at the end of the week to see how it is going. AGS