| 06/06/2008 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 06/05/2008 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* 704-4-5 "FASTENERS SHALL BE OF BRASS OR EQUALLY (STAINLESS) CORROSION RESISTANT MATERIALS" |
|
| 05/02/2008 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* FLOOR LINER OK NEED TO SEE CLOSET FLANGE INSTALLATION |
|
| 04/17/2008 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* FLOORS IN TR'S SHALL SLOPE TOWARD FD AND SHALL BE MADE WATER TIGHT. RED GUARD INSTALLATION REQUIREMENTS SPECIFIY FIBERGLASS MESH BETWEEN FD CLAMPING RIING AND EXTENDING OUT 1' FOOT |
|
| 04/03/2008 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* - LETTER FROM M&C RECEIVED FOR MCU AND FLOOR OUTLET WCS P-4 MS DWV OK TO COVER |
|
| 03/31/2008 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* WATER PIPING OK WATER HEATERS IN RESTROOMS OK SHALL SEE TEST OF FLOOR DRAIN FOR WATERPROOF AND CORRECT CLOSET FLANGE INSTALL |
|
| 03/27/2008 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* PRE-SLAB OK IF FLOOR MOUNTED CARRIERS ARE ALLOWED DWV TEST THRU ROOF OK |
|
| 03/21/2008 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* - JOB OFFICE IS LOCATED IN BUILDING 1161 UNIT 339 - WYE PATTERN FITTINGS ON CO'S OR CAP UPPER LEVEL LAV CO'S - SWEEPS REQUIRED ON TRAP ARMS - TYPE L COPPER SPECIFIED - REAM ALL JOINTS - WATER HAMMER ARRESTORS REQUIRED ON FLUSH O METERS BRANCHES - PROVIDE PROPER WH DRAIN PAN DRAINS - CHAIR CARRIERS AND URINAL CARRIERS SPECIFIED ON FIXTURE SCHEDULE. |