Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2008 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 07/24/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 3RD LIFT/TOP OUT @ CMU DRIVE THRU PIERS - OK TO GROUT |
|
| 07/23/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 9 EXTERIOR CMU PIERS ON WEST & SOUTH SIDES TOP OUT AND 2 CMU PIERS FOR DRIVE THRU 2ND LIFT TO 8'8" OK TO GROUT |
|
| 07/22/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TRASH ENCLOSURE TOP OUT @ 8'8" 9 CMU COLUMN PIERS ON SOUTH & WEST SIDE FROM 4'8" TO 8'8" AND 2 DRIVE THRU CANOPY CMU COLUMNS 1ST LIFT FROM 0' TO 4'8" |
|
| 07/21/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 9 - EXTERIOR CMU PIERS @ WEST & SOUTH OVERHANG FROM 0' TO 4'8" AND TRASH ENCLOSURE FROM 0' TO 4' |
|
| 07/18/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TOTE & BALE ENCLOSURES TOP OUT |
|
| 07/16/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* CMU WALLS @ TOTE & DALE ENCLOSURES FROM 0' TO 8' 8" AFFE - OK TO GROUT |
|
| 07/10/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* BUILD OK |
|
| 07/09/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TOP A/1-4; 4/A-E; E/3-4 |
|
| 07/07/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* G.L A.0 - E.0/1.0 - 4.0 16'8" - 20'8" OK |
|
| 07/01/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4TH LIFT TO 16 FOOT 8 INCH -- OK TO GROUT |
|
| 06/27/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* ALL FOUR PERIMETER CMU WALLS 3RD LIFT - OK TO GROUT SPECIAL INSPECTION PERFORMED |
|
| 06/26/2008 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 06/24/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 2ND LIFT TO 8 FOOT 8 INCH ON ALL FOUR EXTERIOR CMU WALLS -- OK TO GROUT |
|
| 06/23/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1ST LIFT TO 4 FOOT AFF @ WEST CMU WALL |
|
| 06/20/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1ST LIFT FROM TOP OF STEM TO 4 FEET @ NORTH, SOUTH, EAST - EXTERIOR CMU WALLS |
|
| 06/18/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STEM OK |