Inspection History Details
Inspection Status: Approved
Inspection History: ROOF NAILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2009 | ROOF NAILING | Approved | IVRS - Inspection :* | |
| 03/16/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* PROGRESS OK RECALL FOR ARMANDO TO LOOK AT |
|
| 03/04/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* PROGRESS AREA |
|
| 03/03/2009 | ROOF NAILING | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 02/27/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* HIGH ROOF AND BOTH WINGS |
|
| 02/23/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* EAST SECTION OF BUILDING 5 |
|
| 02/20/2009 | ROOF NAILING | Denied | IVRS - Inspection : INCOMPLETE |
|
| 02/03/2009 | ROOF NAILING | Not ready for Inspection | IVRS - Inspection :* | |
| 12/22/2008 | ROOF NAILING | Not ready for Inspection | IVRS - Inspection :* | |
| 12/08/2008 | ROOF NAILING | Partial Approval | IVRS - Inspection :* GL F-G, 1-9 DECKING |