Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2008 | MECHANICAL - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 03/05/2008 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* - CHECKED 1ST LAYER OF FIRE WRAP - OK TO PROCEED WITH 2ND LAYER - PROVIDE DETAIL ON ELEC. PLANS FOR WIRING OF HEAT SENSOR |
|
| 02/29/2008 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* CONFIRMED KITCHEN WALL IS FRAMED WITH METAL OK 1ST LAYER OF FIRE WRAP |
|
| 02/20/2008 | MECHANICAL - INTERMEDIATE | Partial Approval | CHECKED WELDS ON GREASE DUCT. OK FOR 1ST LAYER OF FIRE WRAP 2 LAYERS ARE REQUIRED AS PER 2006 IMC IF BACK WALL IS FRAMED WITH WOOD, 18" CLEARANCE WILL BE REQUIRED FROM HOOD TO WALL. NEED TO SEE WHAT WALL IS FRAMED WITH. |