Date Description Inspector Results Comments
08/25/2008 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
08/20/2008 PLUMBING - INTERMEDIATE Denied IVRS - Inspection :
See detailed listing on site.| 999*
USE APPROVED LINING MATERIALS W/MESH AROUND CLAMPING RING AND SEAL TO 3" ABV FLOOD LEVEL
08/07/2008 PLUMBING - INTERMEDIATE Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) PM INSPECTION REQUESTED
2) NO ACCESS DUE TO GLUE ON FLOOR
07/31/2008 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
CLOSET FLANGES OK
SHOWER PAN LINERS SHALL BE INSTALLED AND INSPECTED PER UPC INSTALLATION STANDARDS #4 PG. 313
HANDOUT PROVIDED
04/10/2008 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
CORRECTION ON VENT OK
NEED TO SEE CLOSET FLANGES AND ABV CEILING JUST PRIOR TO CEILING GRIDS
04/08/2008 PLUMBING - INTERMEDIATE Denied IVRS - Inspection :
See detailed listing on site.| 999*
YOU STILL HAVE A 1/4 BEND ON A VENT WHICH IS BELOW THE FLOOD LEVEL OF THE FIXTURE
04/04/2008 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
- SWEEP REQUIRED ON BELOW FLOOD LEVEL VENT
- TEST ON DWV LEVEL 3 TO CEILING HEIGHT NORTH OF HALL
- TEST ON VENTS TO L4 ON SOUTH SIDE OK
- OK TO COVER WALLS
04/02/2008 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
- LEAK ON VENT T 2ND LEVEL
- TEST ON DWV ON SOUTH SIDE OF HALL FROM CEILING OF L2
TO CEILING OF L3
- PROVIDE TEST ON ABV CEILING REVENTS
- NORTH OF HALL 1/4 BENDS ON DRAINS, CARRIERS NOT SECURED
- NOTE: REINSPECTION FEES MAY BE ASSESSED IF CONTRACTOR FAILS TO CORRECT ISSUES.
03/28/2008 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
COMPLY WITH PAST NOTES, PROVIDE WATER TIGHT TEST ON DWV, SUPPORT & SECURE LAV CARRIERS
03/26/2008 PLUMBING - INTERMEDIATE Denied IVRS - Inspection :
See detailed listing on site.| 999*
WATER ON PIPES
SLOPE
SUPPORTS
SWEEP
90 DEG'S ON DRAIN ARMS
IP HANGERS ON CU
BRASS PLUGS ON FUTURE VALVE LOCATIONS
02/28/2008 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
LEVEL 3 COPPER PRESSURE TEST OK
INSULATE PER SPEC. PROVIDE NECESSARY CLEARANCE
SUPPORT PIPING, CLAMPS, SECURE VERTICAL DROPS
REMOVE ANY EXCESS FLUX
BE SURE INSTALLERS ARE REAMING ALL JOINTS