Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2008 | PLUMBING - GAS PRESS TEST FNL | Approved | IVRS - Inspection :* | |
| 11/14/2008 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* | |
| 11/10/2008 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* 4" GAS PIPING TO BACK UP GENERATOR TEST OK |
|
| 11/06/2008 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* TEST NOT HOLDING FOR OUTSIDE PIPING |
|
| 10/29/2008 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* 1. ADD SUPPORT ON WEST END OF BUILDING FOR GAS AND PROVIDE APPROVED SUPPORT ON ROOF 2. COMPLETE GAS PIPING TO BACK UP GENERATOR 3. PSI TEST STUB OUT OF BLD. TO ROOF |