Permit: T07CM04342

Parcel: 117120220


Addresses:

61 E CONGRESS ST

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
01/11/2010 EXCAVATION/LAYOUT REBAR & ZON Approved
03/10/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STAIR FOOTINGS REINSTALLED PER PLAN. OK TO PLACE CONCRETE.
03/07/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval #6 VERTICALS INSTALLED WITH ONLY 24" LAP SPLICE INSTEAD OF 66" PER PLAN.
#5 AND #6 STEEL INSTALLED IS 40 KSI INSTEAD OF PLAN REQUIRED 60 KSI.
INSTALLER HAS PUT IN TOP MAT OF REINFORCING THAT IS NOT ON PLAN.

SUPERINTENDENT NOTIFIED THAT NEW CALCULATIONS WOULD BE REQUIRED FOR CHANGES TO FOOTING. ANY CONCRETE PLACEMENT WOULD BE AT HIS OWN RISK.
03/06/2009 EXCAVATION/LAYOUT REBAR & ZON Denied 1) MISSING #6 VERTICALS PER KEYNOTE 5 PP S1.1. 2) MISPLACED AND MISSING TOP BARS IN FOOTING PER DETAILS 8 & 9 PP S1.3. 3) CONTRACTOR UNAWARE OF REQUIREMENT FOR SPECIAL INSPECTIONS NOTED IN GSN's AND REQUIRED BY CHAPTER 17 OF THE IBC.