Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2015 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 06/12/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) ALL EXTERIORS OK TO GROUT AND FRONT COLUMNS ALL TOPPED OUT |
|
| 05/20/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT AT COLUMNS OK |
|
| 05/08/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK AT TOP OUTS AT NORTH AND EAST WALLS TO GROUT |
|
| 04/29/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK TO GROUT AT EXT. |
|
| 04/24/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* INSPECTED AND OK TO CONTINUE ON WEST, EAST & SOUTH WALL TO NEXT LIFT ONLY NORTH - NEEDS REBAR VERTICALS FOR NEXT LIFT |
|
| 04/18/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO GROUT ALL EXTERIORS AT 4' FT |