| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2009 | ENGINEERING - FINAL | Approved | Contractor complete punch list. | |
| 02/17/2009 | ENGINEERING - FINAL | Partial Approval | 1- Install all wheel stops. 2- Paint bollards. 3- Extend striping for parking on south side. |
|
| 01/21/2009 | ENGINEERING - FINAL | Partial Approval | Contractor needs to address width of sidewalk (5') and parking spaces (16'). If parking spaces to remian 16' contractor will need to install 7' wide sidewalk and also address over hang at HC ramp. | |
| 01/13/2009 | ENGINEERING - FINAL | Partial Approval | Met with Dennis on site. Walked site went over approved drawings. All ramps no more then 8.33% with a 2% cross slope. Sidewalks no more then 5% slope with a 2% cross slope. All HC parking no more then 2% in all directions. | |
| 10/20/2008 | ENGINEERING - FINAL | Partial Approval | Walked site with super. Went over all slope requirements and truncated dome placement. |