Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T07CM04127


Addresses:

8940 E RITA PARK DR

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
12/16/2008 BUILDING PRE-SLAB Approved IVRS - Inspection :*
09/17/2008 BUILDING PRE-SLAB Denied IVRS - Inspection :
See detailed listing on site.| 999*
NON-APPROVED REPAIR OF LIGHT POLE BASE IN SOUTHEAST CORNER OF SOUTH PARKING LOT THAT WAS OVER-POURED
MUST REMOVE CASSION COMPLETELY AND RE-POUR NEW CAGE W/ANCHOR BOLTS
08/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1) MAN DOOR CONCRETE LANDINGS 5 AT WEST SIDE AND 3 AT SOUTH SIDE
07/21/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
CLOSURE POUR @ GRID Q/20 TO 28 OK
07/17/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
CLOSURE POUR @ GRID LINES Q/12 TO 21
07/10/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SLAB POUR BACK LINE 28 APPROX. D-L OK
07/01/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1. LAST FOUR DOCK LEVELER PIT FLOORS @ N/E CORNER
2. VEHICLE RAMP REINFORCEMENT STEEL @ N/E CORNER
3. 5 MAN DOOR STAIR FOOTING @ A/16 TO 24
4. ENTRY SLAB @ ADMIN. @ SOUTH SIDE
06/18/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
POUR BACKS OK LINE 12-14 BREAKROOM - FINISH DOWELS EAST END
06/17/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PARTIAL APPROVAL @ SUPER SLAB
REINFORCEMENT STEEL @ 26 TO 26.5/F.1 TO P.5
06/16/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
06/13/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SUPER SLAB @ GRID LINES F.1 TO P.5/27.5 TO 28
FOOTING FOR VEHICLE RAMP BETWEEN 27 & 28/A AND 1 STEPS GUARD HOUSE OK
06/12/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
2ND FLOOR MEZZANINE STEEL REINFORCEMENT AT DECK OVER TRUCKERS BREAK ROOM/INBOUND AREA - OK TO POUR
06/11/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SUPER SLAB REINFORCEMENT STEEL @ GRID LINES
P.5 TO F.1/26.5 TO 27
06/10/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
06/09/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SUPER FLAT SLAB @ 26 TO 26.5/F.1 TO P.5 AND EMERGENCY
GENERATOR PAD SOUTH SIDE
06/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
VNA SUPER FLAT SLAB @ GRID LINES 25 TO 25.5/F.1 TO P.5
06/05/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PUMP HOUSE FLOOR SLAB OK
06/04/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
HIGH SPEED LANE @ GRID LINES 12 TO 13/B.6 TO Q -- OK
06/03/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
25.5 TO 26/F.1 TO P.5 @ HIGH SPEED AISLE
06/02/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
05/30/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
CLOSURE POUR AROUND DOCK LEVELER PITS @ GRID A/1 TO 8
05/29/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
05/28/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
05/21/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES 24.5 TO 25/F.1 TO P.5 AND 24 TO 28
P.5 TO Q -- OK TO POUR
05/19/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
DECK @ MEZZANINE ABOVE PERSONNEL OFFICES
05/16/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
BALANCE CLOSURE POUR @ GRID Q/1 TO 12 AND ACCESS RAMP SLAB @ N/W CORNER OF EXTERIOR OF BLDG.
05/15/2008 BUILDING PRE-SLAB Partial Approval STEEL REINFORCEMENT @ PANELS #Q/1 THRU 12
05/14/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES 24 TO 24.5/F.1 TO P.5 AND CLOSURE POUR @ GRID LINE #1/Q TO H.3
05/13/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
05/12/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
05/09/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINE 23.5 TO 24/K.1 TO F.1
05/08/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
CLOSURE POUR @ TILT UP @ MIN INTER TOP WALLS AND PRE-SLAB @ GRID LINES 23.5 TO 24/F.1 TO K.4
05/07/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
ALL PROGRESS OK
05/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
05/05/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
ALL PROGRESS OK
05/01/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/30/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/29/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELLED
04/25/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/24/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ SLAB ON GRADE @ GRID
LINES #25 TO 25.5/F.5 TO K.1
04/23/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
04/22/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
REINFORCED SLAB ON GRADE CONCRETE @
GRID 24 TO 24.5/F.5 TO K.1
04/14/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/11/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/10/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/09/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SLAB ON GRADE @ GRID LINES B.6 TO K/28 TO 25
04/08/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
TILT WALL PANELS REINFORCEMENT STEEL & EMBEDS PANELS #1/H & Z AND A/7,8,10,11 AND 12
04/07/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/05/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES A TO B/12 TO 15 OK
SPECIAL INSPECTOR HAS INSPECTED AND ACCEPTED

PAID AFTER HRS. INSP. PD. $150.00 CHECK #630984
04/04/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/04/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES B.6 TO F/20 TO 24
04/02/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
04/01/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/28/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
03/27/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/26/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
LOADING DOCK SLAB REINFORCEMENT AT
GRID LINES A TO B/15 TO 28 - OK
03/25/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
HUNTER CONST. TREACHER BROKE DOWN - WILL RECALL
03/24/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/22/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES B.5 TO F/13 TO 20

PAID AFTER HRS. INSP. W/CHK#630959 - $175.00
03/21/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/20/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/18/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/17/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/14/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/13/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/12/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRESLAB @ GRID LINES F TO K/16 TO 20
03/11/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
03/10/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES K TO Q/16 TO 20
03/07/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES K TO P.5/16 TO 20 OK
03/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES F TO K/12.5 TO 16
03/05/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ SLABS AT 12 TO 28/B TO B.5 AND
13 TO 16/K TO F
03/04/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
02/28/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES
1 TO 4/F TO K OK
02/27/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
02/26/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
02/25/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
SLAB @ GRID LINES 4 TO 8/F TO K AND B.6 TO F/1.2 TO 4 OK
02/21/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
CANCELED
02/20/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB @ GRID LINES 1 TO 4/K TO P.5 AND 4 TO 8/B.6 TO F OK
02/19/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
AT GRID LINES N TO P/8 TO 12 - PRESLAB OK
02/15/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
RAINED OUT
02/12/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
REINFORCEMENT STEEL & PRE-SLAB @
GRID LINES 4 TO 8/K TO Q
02/11/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PRE-SLAB REINFORCEMENT STEET AND PAD @ GRID LINES
1 TO 12/A.3 TO B -- OK TO POUR
02/08/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PARTIAL APPROVAL @ GRID LINES 8 TO 12/F TO K -
OK TO POUR
02/07/2008 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection :*
02/06/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
02/05/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
AT GRID LINES 8 TO 12/K TO N -- OK TO POUR
01/31/2008 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT IN HIGH SPEED TRAFFIC AISLE SLAB @ GRID LINES 1 TO 12/B TO B.6 AS PER S1.2/4 AND S1.2/12
OK TO POUR