Permit: T07CM03855

Parcel: 118050010

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
08/07/2009 MECHANICAL - INTERMEDIATE Approved IVRS - Inspection :*
07/22/2009 MECHANICAL - INTERMEDIATE Denied IVRS - Inspection :
See detailed listing on site.| 999*
07/10/2009 MECHANICAL - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) CHECKED 100 PSI TEST HYDRONIC PIPING HOT AND COLD EAST MECH. MEZZANINE. OK TO COMPLETE INSULATION
06/11/2009 MECHANICAL - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) CHILLER AND HOT WATER PIPING FROM ROOF PENETRATION TO AIR HANDLER NOT HOLDING PRESSURE
05/12/2009 MECHANICAL - INTERMEDIATE Partial Approval IVRS - Inspection :*
100 PSI TEST ON CHILLED AND HOT PIPING ABOVE GYM AND CORRIDOR AND OFFICE VAV's -- OK TO INSULATE
04/24/2009 MECHANICAL - INTERMEDIATE Partial Approval IVRS - Inspection :*
02/06/2009 MECHANICAL - INTERMEDIATE Partial Approval IVRS - Inspection :*