Inspection History Details
Inspection Status: Approved
Inspection History: ROOF NAILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/16/2009 | ROOF NAILING | Approved | IVRS - Inspection :* | |
| 04/10/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* UPPER & LOWER ROOF COMPLETE CRICKETS & SCUPPERS INSTALLED AS PER PLANS OK TO DRY-IN PROGRESS AREAS |
|
| 04/01/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* MID-PORTION HIGH SECTION OK TO SOUTH ORANGE LINE * NEED RFI FOR PLACEMENT OF MECHANICAL UNITS ON CRICKETS |
|
| 03/26/2009 | ROOF NAILING | Not ready for Inspection | IVRS - Inspection :* PERIMETER OF HIGH ROOF SHEATHING NOT NAILED OFF |
|
| 03/11/2009 | ROOF NAILING | Partial Approval | IVRS - Inspection :* 2ND FLOOR MEZZANINE ROOF @ LINES D-6 TO E/4.2 OK TO DRY IN PROGRESS AREAS |