Permit: T07CM03809

Parcel: 13305054L


Addresses:

8711 E SPEEDWAY BL


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T07CM03809

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
11/16/2009 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
01/14/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EAST STAIRS & LANDING (LINE E/1) AS PER DETAIL #129, S4-1, OK TO POUR
01/09/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS FOR INTERIOR RAMP @ LINES D/1 TO D.1/1
OK TO POUR RAMP
12/24/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STAGE AREA: ADDITIONAL LIFT OF 12"; BOND BEAM WITH #4 REBAR, ANCHOR BOLTS AT 16" ON CENTER
2) ELEVATOR PIT: FOOTING AT 0'-4' WITH 4 AT $5'S HORIZONTAL; #4 VERTICAL DOWELS AT 12" ON CENTER
12/18/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
ELEVATOR PIT FOOTING AS PER DETAILS #141, 142
OK TO POUR
12/15/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
NORTHSIDE STAIRS @ LINE A/2-2.1
OK TO POUR PROGRESS AREA
11/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
N.WEST CORNER OF PARKING LOT -- APPROX. 30' OF SCREEN WALL FOOTING
11/17/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SCREEN WALL FOOTING EAST - SE PORTION,
OK TO POUR PROGRESS AREA
11/13/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SCREEN WALL FOOTINGS; EAST PARKING LOT EAST SIDE
MIDPOINT - SOUTH: APPROX. 140 L.F (NOT TO INCLUDE FAR SE PORTION)

OK TO POUR PROGRESS AREA
11/06/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EAST PARKING LOT
EAST SCREEN WALL FOOTING
OK TO POUR PROGRESS AREA
11/05/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1 @ LIGHT POLE CAISSON -- OK TO POUR
10/28/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
- LIGHT POLE CAISSON FOOTINGS 16 @ AS PER SK2
DATED 4/10/08
- NORTH RAMP AS PER DETAIL #130; PAGE S4.1
OK TO POUR PROGRESS AREAS
10/23/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
2 @ C5/F4 COLUMN FOOTINGS
8 @ C4/F3 COLUMN FOOTINGS @ SOUTH SIDE
10/08/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CMU RAMP LANDING WALL - DETAIL #130 PAGE S4.1
RAMP UP -- OK TO POUR
10/02/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EAST WALL FOOTING LINE A/6 TO F/6 INCLUDING COLUMN FOOTING C1/F5 -- OK TO POUR
09/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. NE CORNER MECH./ELEC. AREA INFILL TO A.3
2. BOOKSTORE/SECTION 100 STEPS INFILL
09/18/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING FOR RAISED WALKWAY; LINE 2.1-4
COLUMN FOOTING @ LINE 6/A -- OK TO POUR
09/17/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
TOE-DOWN FOOTINGS WITH VERTS EPOXIED @ 32" O.C
LINES C.5/4 TO E.2/2 -- OK TO POUR
09/10/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SW CORNER COLUMN FOOTING AS PER SK6 (*)

(*) SOUTH WALL FOOTINGS @ LINES F/2-F/4.1 AS PER DETAILS
#124 & 125; WEST WALL FOOTING E.2/1 - F/1
OK TO POUR PROGRESS AREAS
08/27/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TOE DOWN FOOTINGS FOR STAIR SECTION #3;
BOOKSTORE DOWNSTAIRS @ E.1/1 TO E/1;
STAIRS @ D.1/1 TO D/1 OK TO POUR PROGRESS AREAS
08/20/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
COLUMN FOOTING @ A.2/2.1; TOE DOWN FOOTINGS @ A.2/2.5 TO D.1/3
08/14/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS @ LINE A/2 TO A/2.1; TURN DOWN FOOTINGS @ LINES A.1/2 TO E/4

ENSURE WATER AND DEBRIS ARE REMOVED FROM FOOTINGS
08/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING AND COLUMN FOOTING A/1 TO A/2.1
08/01/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTING @ LINE A/2.1 TO A/4.2
OK TO POUR
07/28/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
07/24/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CONCRETE FOOTING @ EAST SIDE DEMISING WALL
LINE: A.2/6 THRU D/6 - AS PER SK-4 DATED 5/1/08
OK TO POUR PROGRESS AREA
07/23/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED - RAINED OUT
06/20/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS @ LINE A.1 TO B AND D TO E.5
OK TO POUR FOOTINGS
06/11/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
7 @ COLUMN FOOTINGS LINE B/5 TO E/5; INTERIOR STAGE STAIR FOOTINGS OK TO POUR PROGRESS AREAS
06/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
INTER COLUMN FOOTINGS EXCEPT FOOTINGS @ LINES D/5.5, D/5.2, B.1/5.5, A.2/2.1, E.1/2.1
06/02/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
05/30/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
4 @ COLUMN FOOTINGS ON LINE D-E.1/4.2 POURED
SPECIAL INSPECTED
05/29/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS LINES A/2 TO A.2/2 AND E/2 TO E.1/2
OK TO POUR PROGRESS AREAS
05/28/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
WEST WALL FOOTINGS LINE B TO F; COLUMN FOOTING (C1/F8)
(C2/F2) - AS PER DETAIL #110 PAGE S4.0 DOWLINGS CHANGED AS PER CHANGE #SK3 (5/1/08) BY GRENIER ENGINEERING INC.
OK TO POUR PROGRESS AREA