Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
Permit Number - T07CM03664
Inspection Description - FRAMING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/30/2008 | FRAMING | Approved | IVRS - Inspection :* 1) FRAMING COMPLETE |
|
12/11/2008 | FRAMING | Partial Approval | IVRS - Inspection :* RECEPTION AREA - WALLS & SOFFIT -- OK TO SHEETROCK |
|
11/17/2008 | FRAMING | Partial Approval | IVRS - Inspection :* ROOMS #172, 173, 175, 176, 168 OK TO SHEETROCK PENDING ELECTRIC INTERMEDIATE |
|
09/17/2008 | FRAMING | Partial Approval | IVRS - Inspection :* ROOM #168, CEILINGS #229, 228, 226, 225, 221 OK TO COVER PROGRESS AREAS |
|
08/25/2008 | FRAMING | Partial Approval | IVRS - Inspection :* PHASE II 2ND FLOOR FRAMING ALL AREAS EXCEPT FOR HARD CEILINGS OK TO SHEETROCK PROGRESS AREAS |
|
07/24/2008 | FRAMING | Partial Approval | IVRS - Inspection :* RC CHANNEL @ CEILING BETWEEN GRID LINES H TO F/3 TO 6 AND 6 TO 7.2/F.5 TO F.9 - OK |
|
06/30/2008 | FRAMING | Partial Approval | IVRS - Inspection :* PHASE I COMPLETE - OK TO SHEETROCK |
|
06/02/2008 | FRAMING | Partial Approval | IVRS - Inspection :* PHASE 1 - ROOM #126 -- OK TO SHEETROCK |