Date Description Inspector Results Comments
04/05/2010 SHEET ROCK NAILING Approved IVRS - Inspection :*
12/04/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BLDG E, ELECTRIC ROOM-OK TO TAPE INTERIOR AND EXTERIOR WALLS
12/01/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) ELEVATOR SUMP PUMP ROOM AND ELECTRIC ROOM OK TO TAPE PROGRESS AREAS
11/24/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) EXTERIOR ELEVATOR
11/19/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) 2ND LAYER ELEVATOR SHAFT
11/17/2009 SHEET ROCK NAILING Partial Approval CORRIDOR BLDG "B" OK
11/16/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) 1ST LAYER ELEVATOR SHAFT PROGRESS AREA AT CORRIDOR BLDG B
11/12/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) PARAPET WALL BLDG B
11/10/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
1) INCOMPLETE
11/09/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) PROGRESS AREA DENSGLASS BLDG B
11/03/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BACK SIDE OF FEATURE WALL BETWEEN A & B
10/27/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) A-B ENTRY WALL SOUTH SIDE
10/26/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
10/08/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) PROGRESS AREA EAST WALL BLDG "E"
10/07/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :$
1) PENTHOUSE PROGRESS AREA
10/05/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
10/02/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
1) NO PROGRESS MADE
10/01/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
09/30/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BLDG 'E' TOWER PROGRESS AREA
09/28/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) PROGRESS AREA SOUTH WALL BLDG E (DENSE GLASS)
09/25/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BLDG "E" PROGRESS AREA SOUTHWALL DENSE GLASS
09/24/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BLDG E PROGRESS AREA DENSE GLASS
09/23/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) PROGRESS AREA DENSE GLASS BLDG E
09/22/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) WALL EXTERIOR DENSE GLASS BLDG E
09/03/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
BUILDING E - TOP OF CORRIDOR
08/19/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) HIGH ROOF ENTRY OK
08/07/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) BLDG A DENSE GLASS
07/30/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
BUILDING A DENSGLASS
07/14/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
07/06/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) DERSGLASS ON PARAPETS OK
07/01/2009 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
1) DENSE GLASS PROGRESS AREA
06/30/2009 SHEET ROCK NAILING Not ready for Inspection IVRS - Inspection :*
1) DENSGLASS IS NAILED AT 8" CENTER
10/21/2008 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
CORRIDOR BUILDING D - 2ND FLOOR
10/14/2008 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
ONE SIDE OF CORRIDOR BUILDING D