Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T07CM03581
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/05/2010 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 03/22/2010 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 03/19/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WEST COURT AND COMPACTOR PAD-INSPECTED 3/18/10 |
|
| 03/08/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STAIRWAY LANDINGS OK |
|
| 03/04/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* STEPS AT WATER FEATURE EXCLUDES LANDING |
|
| 03/02/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) LOWER HALF OF STEPS |
|
| 03/01/2010 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 02/25/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CMU WALL FOOTER WEST TRUCK COURT |
|
| 02/16/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) TRUCK LOADING AREA AT NEW ENTRY AREA-WEST SLAB APPROX 10' X 30'-OK TO POUR SLAB |
|
| 02/10/2010 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 01/20/2010 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 2 LIGHT POLE BASES |
|
| 12/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STEM NORTH OF RFI GL U/0-50' EAST OF N.W. CORNER OF NEW BLDG 0-4" |
|
| 12/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) WORK INCOMPLETE |
|
| 12/02/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 11/23/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 11/12/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) STEM FOOTER AT ELEVATOR |
|
| 11/05/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR PIT BLDG E |
|
| 10/29/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BLDG E ESCALATOR PIT OK |
|
| 10/28/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/27/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NORTHEAST CORNER BUILDING B |
|
| 10/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/22/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WATER FEATURE AT BLDG C |
|
| 10/14/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BLDG A GL V.0-X.0/16-17.0 2) BLDG C GL Y.0-24.0-26.0 3) BLDG E GL 5.8-T.5/38.5-38.8 ESCALATOR P.T. |
|
| 10/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) WATER FEATURE AREA OK 2) AFTER HOURS INSPECTION PAID WITH CHECK #9189803244 FOR $150.00 |
|
| 10/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BLDG B GRADE BEAM, AND EXCAVATION GL X-X.5/20 |
|
| 10/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) COLUMN FOOTERS GL W.O/18.2-20.6 (4), X.0/18.2 (1), 20 WEST OF V.2/18.0 |
|
| 10/01/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL T.7-T/40.7, CONCRETE WALL AT ELEVATOR |
|
| 09/30/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 4.8/37-39 |
|
| 09/25/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GRADE BEAMS ON REI BLDG OK 2) ELEVATOR PIT AT BLDG 'E' |
|
| 09/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/22/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 10 COLUMN FOOTER AT REI BUILDING |
|
| 09/17/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) INFO ONLY |
|
| 08/28/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 08/25/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) A.6-0.8/1.0 5 TOTAL AB'S 2) A.0/1.0-50 5 TOTAL AB'S 3) A.0-A.6/1.6 1 TOTAL AB'S 4) AFTER HOURS INSPECTION CHECK #5727 $150.00 |
|
| 08/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) MISSING REBAR |
|
| 08/19/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 3 LIGHT POLE BASES |
|
| 08/14/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BLDG A-EAST SIDE (N-S STEM WALL-APPROX 20', BLDG B-EAST SIDE (N-S STEM WALL-APPROX 12') OK TO POUR PROGRESS AREAS 2) SPECIAL INSPECTED FOR PLACEMENT AND EPOXY AT REBAR |
|
| 08/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PROGRESS ON SOIL NAILS SHOT CRETE ON GOING |
|
| 08/11/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PROGRESS WORK ON SOIL NAILS AND SHOTCRETE ON GOING |
|
| 08/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/07/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PROGRESS WORK ON SOIL NAILS ON NORTH AND WEST WALLS, WIRES IN PLACE WITH RODS, READY FOR SHOT CRETE 2) SHOT CRETE ON NORTH WALL 3) AFTER HOURS INSPECTION FOR SATURDAY 8/8/09 CHECK #5002 FOR $300.00 8/8/09 AND 8/9/09 4) GL 40.6/T/U.8 |
|
| 08/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 36.2-39.9/U.8 |
|
| 08/05/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 08/04/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) COLUMN FOOTER GL 40/T.7 |
|
| 08/03/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) NEED PAPERWORK, APPROVALS ON ALL SOIL NAILS |
|
| 07/31/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PROGRESS ON ? NAILS |
|
| 07/30/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 07/29/2009 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NEED APPROVED PLANS |
|
| 07/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 39-39.9 ONLY/T-7 |
|
| 07/23/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) INCOMPLETE |
|
| 07/21/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) FOOTING AT LINE T/7-38-39; DETAIL #8, PAGE S501, 2 AT COLUMN FOOTINGS (F-5) LINE U.8/39.4-39.9; DETAIL #13 (OK TO POUR AREAS) PAGE S501 |
|
| 07/17/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) COLUMN FOOTINGS AT LINE U8/39.9-39.4 PER DETAIL 13/S501-OK TO POUR PROGRESS AREAS |
|
| 07/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PROGRESS AREA BLDG "D" |
|
| 07/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) INCOMPLETE |
|
| 06/30/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BLDG 'A' EAST SIDE |
|
| 06/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) GL 14,15,66-3 COLUMN STEMS |
|
| 06/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GL 32-34/T |
|
| 06/15/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L. W/16.9-17; W/14-14.4 |
|
| 10/31/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* OK TO PLACE WHAT SP. INSP. APPROVES |
|
| 10/24/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONTINUOUS FOOTINGS 140168/U-X & COL. FOOTING @ X/168 PER KLEINFELDER OK |
|
| 10/22/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SOUTHWEST CORNER BUILDING C |
|
| 10/20/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 10/16/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ELEC. PAD BUILDING D |
|
| 10/15/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L 32.2 - T - 34 |
|
| 10/09/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) G.L. 4-RB-225 |
|
| 10/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/21/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* STORMWATER DRAIN FOOTER |
|
| 09/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GRID LINES T.7/32.2-34.8 T.7-U.8/322 T.7/32.2 - 34.8 (4 COLUMNS) U.8/32.2 - 34.8 (4 COLUMNS) AFTER HRS. INSP. CK#1090 -- $150.00 |
|
| 09/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 09/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 08/13/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L Y.0/22.5-23 |
|
| 05/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ELEVATOR PIT |
|
| 05/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* IMBEDS IN PLACE G.L RB-5-6 R1-R28 0'-19' AFFE |
|
| 05/06/2008 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* MISSING INBEDS |
|
| 05/05/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONCRETE WALL G.L RB.5/R1-R2.5 0"-18" |
|
| 04/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L RA/R3.2 R8/R3.2 BB.6/R3 Y.D/RI |
|
| 04/17/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L RF - R4 - RF.2 |
|
| 04/10/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G.L U.8/27.6-30.4 (5 COLUMNS) T.8-U.8/30.4, U8/28.2-30.4 U6 - U8/27.6 - 28.2 |
|
| 04/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN FOOTER G.L RB/R6, RC/R7, RA/R 5.8, R6/R7, R09-RG.1/R8 |
|
| 04/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN FOOTERS G.L R2, RE, RD R3-RE,RD R4-RD, R5-RD, R7-RF-RE |
|
| 03/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | G.L RF/F3 1 COLUMN G.L R4/RE 1 COLUMN G.L R4/RC 1 COLUMN PARTIAL: PLANTER FOOTINGS - OK TO POUR G.L RC-RE/R2-R3 6 COLUMNS G.L R6-R7/RF 2 COLUMNS G.L R5-R7/RC-RE 8 COLUMNS |