Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/15/2009 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 06/18/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ROOMS #111, 158, 129 AND 104 CLOSET FLANGES OK |
|
| 05/29/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* CLOSET FLANGE OK IN ROOMS 139 & 140, 102, 118, 114, 108, 109 |
|
| 05/22/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* TOILET ROOMS 131-133 AND IN CORRIDOR 5 CLOSET FLANGES (ONLY) |
|
| 05/15/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* #157, 155, 153, 151, 147 CLOSET FLANGE OK |
|
| 04/21/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. CALL IN ALL INSPECTIONS OTHER THAN INTERMEDIATE AND FINAL 2. CALL BACK FOR CLOSET FLANGE INSPECTION |
|
| 01/29/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* CALL BACK FOR CLOSET FLANGE |
|
| 01/28/2009 | PLUMBING - INTERMEDIATE | Partial Approval | ADD SUPPORT AND PROTECTION ALL PIPING | |
| 01/14/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* IN WALL AND ABOVE CEILING EAST OF VILLAGE #128 TEST OK |
|
| 01/12/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. RESTROOM #140 AND 139 INSTALL HOT WATER PER APPROVED PLANS 2. INSTALL F/W WATER IN PRE-SCHOOL ROOM #130 & 129 PER PLANS 3. ROOM ON EAST SIDE OK |
|
| 01/08/2009 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* |