Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2008 | BUILDING - FINAL | Approved | IVRS - Inspection :* INCLUDING PHASE #1 UPGRADES OF ACCESS ROUTES ONLY BALANCE OF ACCESS ROUTES TO BE COMPLETED IN PHASES #2 AND #3 |
|
| 08/28/2008 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 08/13/2008 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* COMPLETE ACCESSIBLE ROUTE INDICATED BY LEERAY FOR PHASE 1 GAS CARDS LEFT ON SITE |
|
| 08/07/2008 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) HAVE ACCESS ISSUES THAT MUST BE ADDRESSED |
|
| 07/01/2008 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* UNITS ONLY #124 THRU #133 BLDG "G" UNITS ONLY COMPLETION OF FINAL FOR THIS PERMIT PENDING COMPLETION OF SITE ADA REQUIREMENTS |
|
| 06/20/2008 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* NEED TO CLEAN UP PATIO AREAS OF STUCCO, ROCK AND TRASH |
|
| 05/16/2008 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* MUST HAVE MECH., ELEC., AND PLUMBING FINALS PLUS FIRE APPROVAL BEFORE BLDG. FINAL |
|
| 10/25/2007 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* |