Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2008 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 09/25/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED |
|
| 09/24/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. SEAL TEMPERATURE & PRESSURE RELIEF DRAIN PIPE PENETRATION INTO BLD. AS WELL AS ALL GAS LINE PENETRATIONS. 2. PROVIDE A HOSE CLAMP FOR HIGH LOOP OF DISHWASHER DRAIN 3. HAVE ALL FIXTURES FUNTIONAL 4. FLUSH ALL FIXTURES BOTH HOT & COLD THOROUGHLY LIST MAY NOT BE COMPLETE GAS TEST IS OK |