Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2007 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 11/05/2007 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED PER HOMEOWNER #991-7987 | |
| 11/05/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) CANCELLED |
|
| 11/02/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) REBAR LAP SPLICES MUST BE A MIN. OF 24" |
|
| 11/01/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) LAP ALL REBAR JOINTS MINIMUM 24" 90'S AT CORNERS |
|
| 10/30/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) MISSING 2-#4 BARS CONTINOUS FOOTER |
|
| 10/12/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NO EXISTING FOOTING 2) PROPOSED FOOTING NOT PROVIDED PER APPROVED DRAWING 3) POST AT CENTER BEAM EAST WALL MUST EXTEND, IN 1 PIECE FROM BEAM TO FTGS 4) ROMEX CONNECTORS REQUIRED-ALL METAL J BOXES STAPLE WIRES WITHIN 12" OF J BOX 5) REQUIRED R-30 CEILING INSULATION WILL NOT FIT IN 2 X 6 RAFTERS 6) ALL J BOXES IN CEILING SHALL BE ACCESSIBLE 7) GROUND ALL METAL BOXES 8) CHECK NEW ELECTRICAL-CANNOT OVERLOAD EXISTING CIRCUIT 9) REVISE DRAWING TO REFLECT AS BUILT 10) HAVE REASON DOING WORK ON SITE AT NEXT INSPECTION |
|
| 10/02/2007 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) NO APPROVED PLANS ON SITE 2) RECALL WHEN READY 3) MAKE SURE ALL WORK IS PER APPROVED PLANS |