Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2008 | ENGINEERING - FINAL | Approved | ||
| 06/12/2008 | ENGINEERING - FINAL | Denied | Complete all striping and H.C. parking rear of building. | |
| 06/06/2008 | ENGINEERING - FINAL | Denied | NEED TO ADDRESS PUNCH LIST DATED 05/30/08 CONTRACTOR HAS ONLY PAVED REAR OF BUILDING (NO STRIPING NO CURB WORK) NO OTHER WORK COMPLETED |
|
| 05/30/2008 | ENGINEERING - FINAL | Denied | Contractor needs to: 1- Close out building shell permit. 2- Complete all site work per approved plans. 3- Separate all construction activity from public access. 4- Separate all construction debris from public acccess. 5- Stabilize all areas disturbed by construction. 6- Complete paving rear of building. 7- Remove port-a-potty from site. 8- Fill all open holes in parking lot. This is not a complete punch list. Contractor will need to call in again. |