Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2008 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 05/28/2008 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* HAVE PERMITS ON SITE |
|
| 05/27/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* CONTINUED "NOT READY" WILL RESULT IN REINSPECTION FEE |
|
| 05/23/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* NO ACCESS AT 8:34 |
|
| 04/05/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE UPC LISTING FOR HAND SPRAYER FOR P-3 SINK |
|
| 02/20/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE BACKFLOW PROTECTION FOR HAND SPRAYER AT P-3 SINK |
|
| 02/07/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. REPAIR LEAK ON WATER HEATER AND INSTALL PER PLAN 2. ADD SUPPORT ON VENT PIPE IN WATER HEATER ROOM 3. PROVIDE VACUUM BREAKER ON ALL HOSE BIBS 4. PROVIDE LADDER TO INSPECT ROOF 5. INSTALL PER PLAN FOR LAV DETAIL 205 |