09/29/2010 | ELECTRIC - CONSTRUCTION POWER | Approved | ||
09/07/2010 | ELECTRIC - CONSTRUCTION POWER | Partial Approval | Re: MLK Tower Electric Power Service Modification Inspection 1 N. 5th Ave. The following is a description of what I witnessed. On 9/3/2010, from approximately 2:40 pm to 3:00 pm the new electric power service to the address above was inspected. The new TEP transformer secondary terminations, the terminations at the buildings busbar, the new service feeder conductors and conduits were reviewed. Each conduit pull was balanced for phasing and the rotation & voltages were checked before the building was re-energized. At approximately 3:00 pm the TEP Maproom was called and given approval for energization of 1 N. 5th Ave, TEP work order 192887, with ECO clearance. At 3:30 pm the TEP power was on and by 3:40 pm the subject buildings main switchgear was re-energized from the new service. After this the individual circuits of the building were re-energized as well. No incidents or disruptions of service were observed. V. John Lundgren, PE City of Tucson General Services Dept. Architecture and Engineering Division John.Lundgren@tucsonaz.gov Office: 520.837.6321 |
|
09/25/2009 | ELECTRIC - CONSTRUCTION POWER | Partial Approval | IVRS - Inspection :* 1) TEMP SERVICE STRUCTURE AT NORTH END OF PROJECT 2) CALLED CLEARANCE INTO KATHY AT TEP 9/24/09-AM |
|
12/15/2008 | ELECTRIC - CONSTRUCTION POWER | Partial Approval | IVRS - Inspection :* 1) OK 3/4" AND 1" PVC FOR ELEVATORS AS MARKED |
|
12/11/2008 | ELECTRIC - CONSTRUCTION POWER | Denied | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* 1. LABELING TO BE PERMANENT 2. FINISH PREVIOUS ITEMS |
|
12/09/2008 | ELECTRIC - CONSTRUCTION POWER | Denied | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* 1. PLEASE HAVE ELECTRICIAN PRESENT 2. LABEL DISCONNECTS 3. INSTALL MAIN BONDING JUMPER 4. BRING NEUTRAL TO SERVICE DISCONNECT - 250.24(C) 5. MAINTAIN CLEARANCES FOR TRANSFORMER -- 450.9 6. SECURE TRANSFORMER TO PAD 7. LABEL BREAKERS PER 408.4 8. INSTALL GROUNDING ELECTRODE CONDUCTOR AND MAIN BONDING JUMPER SAME LUG (XFMR) 9. TIGHTEN LOOSE CONDUCTORS (XFMR) 10. INSTALL REJECTION PINS |