Permit: T07CM03033

Parcel: 117060940


Addresses:

45 N 5TH AV


Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Permit Number - T07CM03033

Inspection Description - BUILDING - PROGRESS

Inspection Status - Approved

Date Description Inspector Results Comments
09/09/2010 BUILDING - PROGRESS Approved TOPPING MATS DONE
09/08/2010 BUILDING - PROGRESS Not ready for Inspection CANCELLED BY DON @ LLOYD
08/23/2010 BUILDING - PROGRESS Partial Approval MASONRY AT WEST SITE WALL OK TO GROUT.
07/27/2010 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) PROGRESS ON PROTECTIVE SLAB
07/13/2010 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) LIGHT POLE BASE SOUTH WEST CORNER AND COLUMN STEM SOUTH EAST CORNER
05/24/2010 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) PROTECTION SLAB OK
05/07/2010 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) INFILL FOR CRANE OPENING OK TOP LEVEL
05/03/2010 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) IN FILL FOR OLD CRANE OPENING 2ND LEVEL OK TOP
10/09/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
10/02/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
09/17/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
RESHORE LOW SLAB AREA NW QUAD LEVEL B2 COMPLETE
09/15/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) SHORE FOR NORTH WEST QUAD LEVEL B-1 OK, LEVEL B2 RESHORE OK TO LINE-FOR LOWER LEVEL STREET ?
09/10/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) SHARING LEVEL B1-OK TO LINE 6
09/02/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) SHORING NORTH EAST QUAD
2) B2-B1 OK
09/01/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
08/17/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) LEVEL B1 SCAFFOLD E-N/1-6 OK
2) LEVEL B2 RESHORE F-N/1-5.5 OK
08/14/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
08/06/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
07/29/2009 BUILDING - PROGRESS Partial Approval RESHORE LEVEL B2 F-N/1-6 OK. LEVEL B1 SHORING NOT YET COMPLETE.
07/14/2009 BUILDING - PROGRESS Partial Approval 1) SHORING OK TO LINE 7
07/13/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
07/09/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1) DECK SHORING OK NW QUADRANT FOR B1
2) SHORING STRIP OK SW QUADRANT FOR B1
05/18/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
ALL SPECIAL INSP. REPORTS REVIEWED THROUGH 5/14/09
05/08/2009 BUILDING - PROGRESS Partial Approval WATERPROOFING PROGRESS LINE 1 OK. LOWER LEVELS NOT COMPLETELY SECURED YET.
04/29/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
ALL SPECIAL INSPECTIONS THROUGH 4/28 ACCEPTED OK
04/20/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1. RE-CHECK SCAFFOLD POSTS AREA K-N/9-10 FOR PLUMB.
2. SCAFFOLD G-K/4-10 OK
04/16/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
SPECIAL INSP. REPORTS REVIEWED & ACCEPTED THROUGH 4/15/09
04/02/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
SOIL NAILS WALLS COMPLETE
03/24/2009 BUILDING - PROGRESS Partial Approval SPECIAL INSPECTIONS THROUGH 3-23 REVIEWED AND ACCEPTED FOR SOIL NAILS AND RETANING SHOTCRETE.
03/20/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
03/18/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
SPECIAL INSPECTION FORMS FOR SOIL NAILS ACCEPTED THROUGH THIS DATE
03/09/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
SPECIAL INSP. REPORTS REVIEWED AND ACCEPTED
THROUGH THIS DATE
02/26/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
02/17/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
02/10/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
02/05/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
1. INITIAL CRANE APPROVALS REVIEWED/APPROVED LAST MONTH
2. SCHEDULED RE-TORQUE OF TOWER CRANE IN PROGRESS
(REQ. EVERY 40 HRS.)
01/29/2009 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
SPECIAL INSPECTIONS ON COMPACTION
REVIEWED THROUGH 1/28/09
01/22/2009 BUILDING - PROGRESS Partial Approval SPECIAL INSPECTION REPORTS FOR COMPACTIONS AND CONCRETE REVIEWED AND ACCEPTED FOR ALL WT WORK THROUGH 1-21-09.
12/16/2008 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
ALL SPECIAL INSPECTIONS FOR DRILLED PIERS AND CAISSONS THROUGH 12/4/08 REVIEWED & ACCEPTED
12/04/2008 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
ALL SPECIAL INSPECTIONS FOR PIERS, STEEL CONCRETE, REVIEWED AND ACCEPTED THROUGH DATES 12/2/08
12/03/2008 BUILDING - PROGRESS Partial Approval IVRS - Inspection :*
PLEASE HAVE SCHNEIDER AND ASSOCIATES LEAVE 2 COPIES OF TOWER CRANE FOOTINGS AT SITE