Permit: T07CM03031

Parcel: 12418162D


Addresses:

931 S HIGHLAND AV

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
06/04/2008 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
05/08/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
CMU WALL TOP OUT - COMPLETE AT PERIMETER WALLS
05/07/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
S. WALL AND E. WALL 20' TO 25' OK TO GROUT
WEST WALL 24' TO 26' SPECIAL INSPECTED

1. EPOXY BOLTS ON TOP OF EXISTING WALL SPECIAL INSPECTED
05/06/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NEED TO SEE INSTALLATION OF SIMPSON PATM25 (1) S4
05/05/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
SO. WALL 16' TO 20'
W. 20' TO 24' 8" CMU
05/02/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12" CMU PERIMETER WALL AT N/E WALL FROM 16' TO 20' AND EAST WALL FROM CORNER SOUTH TO 4TH CONTROL TO 20' AND SOUTH WALL FROM 12' TO 16'
05/01/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12" CMU WALL @ EAST PERIMETER FROM 4TH CONTROL JOINT TO SOUTH CORNER FROM 12' TO 16' AND WEST & NORTH WALL FROM 16' TO 20' AFFE
04/30/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12" CMU WALL @ EAST FROM 2ND CONTROL JOINT TO 4TH FROM 12' TO 16' AND SOUTH WALL TO 12'
04/29/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12" CMU PERIMETER WALL FROM 12' TO 16' AFF
AT NORTH NORTHWEST AND FROM CORNER TO 2ND MASONRY CONTROL JOINT ON EAST WALL
04/28/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
SPECIAL APPOINTMENT INSPECTION @ 9:30 AM (4/28/08)
PAID $150.00 CHK#188974

1. WEST CMU PERIMETER WALL FROM 12' TO 16'
2. EAST CMU PERIMETER WALL FROM 8' TO 12' @ 2/3 LENGTH FROM NORTH END
04/25/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
STEEL REINFORCEMENT @ 12" CMU WALLS ON WEST, NORTH AND NORTHEAST CORNER FROM 8' TO 12' AFF -- OK TO GROUT
04/24/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
2ND LIFT E AND S WALL AND 2ND LIFT W WALL NORTH HALF
04/23/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
CMU WALL REINFORCEMENT AT WEST, NORTH AND N/E WALL
FROM 4' TO 8' AFF AND SOUTH WALL FROM 0' TO 4' AFF
04/22/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT FROM TOP OF STEM TO 4' AFF AT
EAST & NORTHEAST WALLS
04/21/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT FROM 0' TO 4' @ NORTH & WEST CMU WALLS
04/17/2008 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
CMU STEM WALL @ NORTH & WEST PERIMETER WALLS