Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2009 | ENGINEERING - FINAL | Approved | ALL PREVIOUSLY NOTED ITEMS HAVE BEEN COMPLETE AT THIS TIME. A TEMPORARY USE PERMIT IS REQUIRED FOR THE STORAGE FACILITY LOCATED ON THE EAST SIDE OF BUILDING 2. | |
| 10/24/2008 | ENGINEERING - FINAL | Denied | Finish sidewalk to ROW or obtain DSMR remove construction material place dumpster in dumpster encloser finish site work |
|
| 10/15/2008 | ENGINEERING - FINAL | Denied | 1) PROVIDE AN APPROVED GRADING/SITE PLAN SHOWING CHANGES MADE FROM THE ORIGINAL GRADING/SITE PLAN. 2) INSTALL 10' MAINTENANCE ACCESS WAY INTO RET/DET BASIN 3) PROVIDE A RET/DET BASIN CERTIFICATION STAEMENT FROM THE ENGINEER OF RECORD STATING THAT THE BASIN AND DRAINAGE WAYS HAVE BEEN BUILT PER THE APPROVED PLANS. 4) COMPLETE ALL SITE WORK TO INCLUDE PAVING. 5) PROVIDE AN ADA COMPLIANT PEDESTRIAN ACCESS FROM THE RIGHT-OF-WAY TO THE BLDG. 6) FINAL GRADING PERMIT # T07BU01587 |