Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2008 | PLUMBING - FINAL | Approved | NECESSARY CORRECTIONS MADE OK OK TO COVER |
|
| 05/29/2008 | PLUMBING - FINAL | Not ready for Inspection | 1. EXPOSE EXTERIOR DRAIN PIPING FROM HOUSE TO LIFT STATION 2. PAINT VENT TERMINALS 3. INSTALL CLEANOUT ADPTS. WITH PLUG AT CLEANOUTS 4. INSTALL AVB's ON HOSE BIBS 5. PAINT EXPOSED ABS TO LIFT STATION. (ABS SHALL NOT BE INSTALLED IN AN EXPOSED EXTERIOR LOCATION, PAINTED OR NOT) NO OTHER CORRECTION REQUIRED THIS TIME. 6. PLEASE CALL IN ALL REQUIRED INSPECTIONS NOTE: STAND PIPE RECEPTORS P-TRAPS SHALL NOT BE INSTALLED LOWER THAN 6" AFF NOR MORE THAN 18" AFF STAND PIPES SHALL BE 18"-30" IN LENGTH (FOR FUTURE REFERENCE - NO CORRECTIONS REQUIRED THIS TIME) CONTINUED "NOT READY" WILL RESULT IN A REINSPECTION FEE |
|
| 05/21/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. THIS PLAN HAS NOT BEEN REVIEWED BY THE CITY 2. NOT INSTALLED PER PLAN. PLAN CALLS FOR PVC - SIZE DIFFERENCE 3. MAY NOT INTERMINGLE ABS AND PVC 4. PLAN SHOWS GRAVITY DRAIN ON DISCHARGE SIDE OF CHECK VALVE. |