| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2008 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* LINE B/2.3-2.4 PIER FOOTING (F8) DETAIL #8 PAGE S3 TOE DOWN FOOTINGS (EAST SIDE) -- OK TO POUR |
|
| 09/18/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONTINUOUS FOOTING DETAIL #10 PAGE S3 LINE G/1 TO B/5 3 @ F4/C2, 10 @ F2/C2 -- OK TO POUR PROGRESS AREAS |
|
| 09/16/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1 @ COLUMN FOOTING F1/C5 @ C/3.4; 1 @ COLUMN FOOTING F1/C5 @ C.2/2.6 - 2 @ COLUMN FOOTINGS @ F/3-3.3 OK TO POUR PROGRESS AREA |
|
| 09/08/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. 8 @ F1 COLUMN FOOTINGS @ EXISTING BUILDING (COLUMN @ 3/F.1 MISSING) 2. 3 @ F/4 COLUMN FOOTINGS @ ELEVATOR PIT 3. ELEVATOR PIT @ 40" OK TO POUR PROGRESS AREA |
|
| 08/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ELEVATOR PIT FOOTINGS @ B/3.5 TO B.1/4.1 2 @ COLUMN FOOTING C1/F5 @ LINE 2/D-E 1 @ COLUMN FOOTING C1/F4 @ LINE E/2.3 1 @ COLUMN FOOTING C1/F7 @ LINE D/3.3 1 @ COLUMN FOOTING C1/F5 @ LINE D/4.3 OK TO POUR PROGRESS AREAS ELEVATOR PIT CHANGE FOR COLUMNS DATED 8/25/08 |