Permit: T07CM02550

Parcel: 10512024D


Addresses:

4040 N ORACLE RD


Inspection Status: Approved

Inspection History: PLUMBING - PROGRESS

Permit Number - T07CM02550

Inspection Description - PLUMBING - PROGRESS

Inspection Status - Approved

Date Description Inspector Results Comments
07/28/2009 PLUMBING - PROGRESS Approved IVRS - Inspection :*
07/21/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
1) UNABLE TO LOCATE G.C. OR PLUMBING CONTRACTOR
2) SUPPORT VERTICAL EXPOSED PIPING ALONG BACKSIDE OF WALK IN BOXES
07/02/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
1) D.I.P FROM RPPBP TO TIE IN AT BLDG OK
06/29/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
06/26/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/23/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
REMAINING FLOOR SINKS AND CLEANOUTS
ON NORTH HALF OF STORE OK TO COVER
06/22/2009 PLUMBING - PROGRESS Partial Approval FLOOR SINKS AND CLEANOUTS IN GROCERY
ALONG COLUMN 9.5 TO BUT NOT INCLUDING COLUMN 12
ALSO, FROM COLUMN J-2 TO AND INCLUDING COLUMN H
OK TO COVER
06/19/2009 PLUMBING - PROGRESS Denied IVRS - Inspection :
See detailed listing on site.| 999*
REQUIRE APPROVED TRANSITION
COUPLINGS AT FS CONNECTION
06/16/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
1. WATER COOLER DRAIN OK ON WEST SIDE OF BUILDING
2. WASHER BOX TRAP OK ON WEST SIDE OF BUILDING
3. VENT ON WEST SIDE OF BUILDING OK
06/15/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/02/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
04/09/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
NO PLUMBING WORK AT THIS TIME
03/17/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
02/18/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
NO NEW WORK TODAY
02/09/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
NO NEW WORK TODAY
02/05/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
02/04/2009 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
NO NEW PLUMBING WORK TODAY
KEEP CALLING
02/03/2009 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
NO NEW WORK TODAY