Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T07CM02550

Parcel: 10512024D


Addresses:

4040 N ORACLE RD


Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Permit Number - T07CM02550

Inspection Description - REINFORCED MASONRY PRE-GROUT

Inspection Status - Approved

Date Description Inspector Results Comments
08/23/2009 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
07/16/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 250' NORTH SCREEN WALL TOP OUT
07/15/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
1) INCOMPLETE
07/02/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 2ND LIFT 250' NORTH SCREEN WALL
06/30/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 250' 1ST LIFT NORTH SCREEN WALL
06/29/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 250' 1ST LIFT NORTH SCREEN WALL
06/19/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
06/16/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH SIDE COLUMNS
06/15/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH SIDE COLUMNS
06/04/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT NORTH WEST WALL G.L. A/8-13
06/02/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
19'4" WEST WALL NORTH CORNER
06/01/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT AT WEST SIDE SOUTH CORNER
05/27/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
19'4" SOUTH SIDE; 17'4" WEST SIDE SOUTH CORNER
05/26/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
SOUTH FACADE WALL: GRID LINE #1 @ 17'4" (3'8" ABOVE) LINTELS; EAST AND S.E. PORTION OF BUILDING: 7 @ 12" PILLARS @ 12'-16'; OK TO GROUT PROGRESS AREAS
05/22/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
ALL PROGRESS OK
2 DAY STORM SHUT DOWN MUCH AT JOB
05/21/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
05/20/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
05/19/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
8'-12' NORTH SIDE COLUMNS
05/15/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
8'-12' SOUTH SIDE COLUMNS
05/13/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 8'-12' LIFT ON NORTH COLUMN WEST SIDE
05/11/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT EAST SIDE
COLUMN 8'12'
G.L. 8-9/A, 8' LIFT 10/13/A
05/08/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT SOUTH COLUMNS SOUTH SIDE,
EAST COLUMN 4' TOTAL - 1ST LIFT
05/07/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12' AT SOUTHWEST CORNER; 1ST LIFT NORTH SIDE
05/05/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT FRONT COLUMNS NORTH END
05/04/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT EAST SCREEN WALL, 2ND LIFT ON FRONT COLUMNS CENTER OF BUILDING
04/29/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT WEST, NORTH COLUMNS
04/27/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST SCREEN WALL 2ND LIFT/60' SOUTH TO NORTH
04/23/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) 1ST LIFT EAST SCREEN WALL
04/22/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
220' EAST SCREEN WALL 4' LIFT
04/21/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
04/08/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
03/30/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST SCREEN WALL 220'
03/29/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*
03/26/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
2ND LIFT 100' EAST SCREEN WALL;
60' 1ST LIFT EAST SCREEN WALL
03/25/2009 REINFORCED MASONRY PRE-GROUT Denied IVRS - Inspection :
See detailed listing on site.| 999*
NO BOND WIRE INSTALLED
03/23/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST SCREEN WALL 4' LIFT 100' NORTH TO SOUTH
03/20/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST SCREEN WALL 100' NORTH TO SOUTH