Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/04/2008 | ENGINEERING - FINAL | Approved | Landscaping to be completed under Permit T07BU00794. Contractor separated public access from construction activity. | |
| 02/01/2008 | ENGINEERING - FINAL | Denied | Contractor needs to complete all work around buildings 1694 and 1690. Building 1686 contractor needs to complete: 1- Clean parking lot. 2- Remove port-a-pottys. 3- Remove temp fencing around build 1686. 4- Separate all construction activity and debris from public access. 5- Install safety barrier rear of building 1686. 6- Close out grading permit. 7- Complete all paving, adjust all boxes, and address note 13 on the approved drawings. 8- Stripe loading zones 9- Install H.C. signage. Spoke to Mario site super in regards to. |