Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2008 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 01/10/2008 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NEED TO CLEANOUT ALL CELLS TO BE GROUTED SOLID 2) NOT READY FOR INSPECTION-CALL BACK |
|
| 12/06/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO CONTINUE TO NEXT LIFT |
|
| 11/28/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 11/27/2007 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) VERTICAL REBAR NEEDS TO BE PUT IN CELLS TO BE GROUTED 2) NEED APPROVED SET OF PLANS/PERMIT ON SITE |